SmartManager variables
SmartManager variables
SmartManager administers the following set of variables.
Editable on SmartTransfer Pro
Also viewable on:
-
Console
-
SmartDashboard
Variable name |
Description |
Example Data |
Last Updated Time |
When any MES data was last changed |
|
Last Updated By |
Who changed the MES data last |
|
Internal Order Code |
The internal order code relating to the project |
SO1234 |
Process Step |
The step that the job file represents in the project |
2 of 4 |
Total Parts Required |
The number of parts required from the customer |
50 |
Parts Made Per Job |
The number of parts a single job file can produce |
10 |
Stock Material Type |
The type of material required for the job |
Plywood |
Job Size X Axis |
Job size in X |
1000 mm |
Job Size Y Axis |
Job size in Y |
2000 mm |
Job Size Z Axis |
Job size in Z |
12 mm |
Stock Material Size |
The minimum size of stock material required for the job |
1220 x 2440 x 12 mm |
Pre Production Notes |
Any additional notes that the operator may require prior to running the job. These are notes typically issued by the programmer or manager |
Z height datum check is critical. Top surface is customer facing. Ensure deburr on lower face. Clear all swarf between all teeth. |
Primary Operator |
The name of the operator skilled in this job |
Finn |
Job Duration |
The estimated amount of time that this job file will take to complete |
00:15:22 |
End Effector |
Type of end effector used |
Spindle |
Tool Diameter And Type |
The diameter and type of tool used |
6 mm upcut spiral |
Toolpath Name |
Name of toolpath set in CAM stage |
Profile cut |
XY Datum Position |
XY datum position relative to the stock |
Bottom right |
Z Datum Position |
Z datum position relative to the stock |
Stock top |
Maximum Feed Rate |
The maximum feed rate for the job |
6,000 mm/min |
Maximum Plunge Rate |
The maximum plunge rate for the job |
750 mm/min |
Maximum Spindle Speed |
The maximum spindle speed for the job |
25,000 RPM |
Customer Name |
The name of the customer |
Yeti Tool |
Customer Part Number |
The customer's part number |
201598 |
Customer Part Description |
The name of the part that the job file belongs to. A part can be made up of multiple job files |
X racks |
Customer Order Reference |
Typically the purchase order number provided by the customer |
PO4321 |
Parts Made So Far |
The number of parts completed so far |
Editable on Console
Also viewable on:
-
SmartDashboard
Variable name |
Description |
Example Data |
Parts Made So Far |
The number of parts completed so far |
|
Batch Number |
A code relating to the batch of items this item belongs to |
YT394857 |
Post Production Notes |
Notes added by the operator after job completion |
3 tabs broke on part X during final operation |
Machine Name |
The name of the SmartBench (configurable at machine) |
X rack cutter |
Machine Location |
The position of the machine in the factory (configurable at machine) |
Rack cutting room |
Viewable on Dashboard
In addition to all of the variables listed above, the Dashboard also displays the following variables:
Variable name |
Description |
Example Data |
Machine Status |
The current status of the SmartBench |
Idle |
Spindle Overload |
The peak spindle overload seen during the course of running the job file |
20% |
Current Job Time |
The length of time the current job has been running |
1:23:45 |
Current Job Percentage |
Measurement of progress through the job file. This is measured in the number of lines of GCode processed, compared to the total number of GCode lines in the job file. Note that because some GCode lines take longer to effect than others, progress indicated may not correlate exactly with time remaining |
99% |
Z Lube Hours Since Last Maintenance |
Percentage of hours remaining before Z axis needs to be relubricated |
30% |
Z Lube Hours Before Maintenance Required |
Number of hours remaining before Z axis needs to be relubricated |
15 |
Spindle Brush Since Last Maintenance |
Percentage of hours remaining before spindle brushes need to be replaced |
50% |
Spindle Brush Hours Before Maintenance Required |
Number of hours remaining before spindle brushes need to be replaced |
125 |
Calibration Since Last Maintenance |
Percentage of hours remaining before XY calibration needs to be checked |
50% |
Calibration Hours Before Maintenance Required |
Number of hours remaining before XY calibration needs to be checked |
50 |
Current Job Gcode Line |
The last line of GCode to be streamed from the console to the ZHead |
342 |
Actual Job Duration |
Total time job has run for after completion |
34520 |
Actual Job Pause Duration |
||
SmartBench Version |
Version of console software |
V1.8.2 |